Consider two processes P1 and P2 where period P1 = 50, processing time t1 = 25 and period P2 = 75, processing time t2 = 30. Can these two peocesses be schedule using rate-monotonic scheduling? Illustrate your answer using a Gantt chart. 請問這一題該怎麼解?題目完全看不懂= = 且 rate-monotonic 在哪一個章節有提到? 麻煩指導~感謝 -- ※ 發信站: 批踢踢實業坊(ptt.cc) ◆ From: 61.57.104.57
killerjoe:在real time system那一章 01/19 23:57
killerjoe:是用在schedule real time process的 01/19 23:58
assassin88:那請問這題有解嗎? 01/20 00:01
Nandesga:答案是不能schedule 01/20 00:02
assassin88:請問要怎麼看的?? 01/20 00:08
killerjoe:恐龍7th 19.5.1 01/20 00:16
jwcs:不能Schedule, 畫畫看 Gantt chart 大概就知道了 01/20 08:22
RoddickJoe:rate-Monotonic的簡單定義就是period越短的優先權越大 01/22 03:14
assassin88:這題我會了~感謝 01/22 23:21