看板 P_Management 關於我們 聯絡資訊
我小小來灌灌水一下:p po pmp的情境題給 大家娛樂 題目出處:pmp Exam pre by Rita Mulcahy, PMP p.82 有四個選項 Question 15: During the completion of project work, the sponsor asks the project manager to report on how the project is going. In order to prepare the report, the project manager asks all the team members what percent complete their work is. There is one team member who has been hard to manage from the beginning. In response to being asked what percent complete he is, the team member asks, "Percent complete of what?" Being tired of such comments, the project manager reports to the team member's boss that the team member is not cooperating. Which of the following is likely to be the real problem? a. The project manager did not get buy-in from the manger for the resources on the project. b. The project manager did not create an adequate reward system for team members to improve their cooperation. c. The project manager should have had a meeting with the team member's boss the first time the team member caused trouble. d. The project manager does not have work packages. 讓我簡單把故事說一下 你是一個專案的pm 就是在專案進行中時 你的金主問你 "目前工作完成了多少 阿?" 於是你就問所有的team member他們工作進度 唯獨其中一人 從一開始就很不合作 沒回答你問題不說 還態度不好的回你 "完成什麼工作?" 你很不爽 覺得受夠了他 於是把他不合作的情形向他的上司報告 題目就問 造成這情形的真正問題是什麼? a.在專案人力資源的使用上 PM 並沒有得到管理階層的支持 b. pm沒有建立良善的獎勵系統使隊員更加合作 c. 打從一開始這member有製造麻煩的情形時 pm就該跟他的老板會面 d. PM並沒有work package 在pmp考試中 work package = task 也就是 時程和花費已被清楚定義的工作分配 你覺得要選哪一個呢? :) -- 打球別忘找蘇菲雅 沒有程度但有熱度 打歡樂 打歡樂 打歡樂 打歡樂 -- ※ 發信站: 批踢踢實業坊(ptt.cc) ◆ From: 220.130.182.222
RedTear:應該是D 12/19 21:12
birdpon:應該是D 12/19 22:51
vbfish:另外補充一點,sponsor指的是PM的主管,因為每個案子一定要先 12/19 23:06
vbfish:由主管向各function宣布由誰接PM,這樣此PM才開始有舞台的.. 12/19 23:08
yule1224:是d 12/20 08:11