Consider two processes P1 and P2, where the periods are p1 = 50 and p2 = 75 and the processing times are t1 = 25 and t2 = 30, respectively. Schedule the two processes using the following algorithms and illustrate their executions using Gantt charts. CPU time periods P1 25 50 P2 30 75 1.Rate-monotonic scheduling 2.Earliest deadline first -- ※ 發信站: 批踢踢實業坊(ptt.cc) ◆ From: 218.171.55.250