Which of the following is the MOST likely cause of poor risk management ? A: Inadequate risk response planning. B: Poor risk monitoring and control. C: Lack of a prioritized list of risks. D: Lack of detail in the scope statement. There is a probability of 0.10 that a given risk will occur in a project. If it occurs, it will result in a loss of US $10000. The insurance cost for this event is US $700, with a deductible amount of US $250. Should a rational project manager buy this insurance ? A: Yes, since US $1000 is greater than US $950. B: Yes, since US $1000 is greater than US $700. C: No, since the deductible amount changes the expected value of the risk event. D: No, since US $1250 is greater than US $ 1000. 這題答案跟我選的不一樣,但我腦筋轉不出來.... 一整個不明白為什麼..... -- ※ 發信站: 批踢踢實業坊(ptt.cc) ◆ From: 123.194.171.53
louside:第一題是D 因為PSS是Risk mgmt ITTO裡的input 第二題是A똿 05/24 00:46
purist:我看不太懂deductible amount的意思..不可能保費700但 05/24 09:01
purist:賠償只有250吧,那是在減免什麼呢...? 05/24 09:01