今天做題目 有個問題讓我想不出答案..... Managemant has provided you with a project charter, and you are in the process of creating a project scope statement. You have asked the team for input to ensure that the project scope statement is complete. However, the team is struggling woth defining the scope. Which of the following BEST describes the problem ? A. A WBS was not completed before the project scope statement was begun. B. The team is working on the project scope statement without the benefit of organizational process assets. C. The team is in the scope definition process and needs the project scope statement as an input. D. The project objectives were not identified before the project scope statement was begun. 版上有人可以協助解惑和指導嗎? 謝謝~~~~~ -- ※ 發信站: 批踢踢實業坊(ptt.cc) ◆ From: 123.194.165.130
yule1224:是 D嗎 :P 05/06 23:55
peitsung:我認為是C 05/07 17:31
peitsung:有中文嗎?可能更方便了解關鍵語意 05/07 17:31
daimond:C+, 專案章程應該已經清楚描述發起人的目標 05/07 19:59
weiber:我選C 05/07 22:47
ytai:選C的話有點弔詭的地方是,專案範圍說明書是範圍定義的output 05/07 22:56
ytai:但如果要解釋成初步範圍說明書的話,則答案是C沒錯 05/07 22:58
ytai:所以如果是我的話,我會選擇D囉,可以再討論看看 05/07 22:58
chongyu:I would choice "D" :-) 05/07 23:30
daimond:也許C不一定對,選D的理由是?專案目標不是已經在章程中? 05/08 00:32
abase0001:B,根據ITTO, project scope statement的四個input中, 05/08 10:26
abase0001:其中一個是organizational process assets 05/08 10:26
abase0001:(組織過程資產) 05/08 10:27
abase0001:C不對,根據題目,project scope statement是output 05/08 10:30
abase0001:D不對,project objectives已經在charter中了 05/08 10:32
abase0001:A就不用說了,製作WBS還太早 05/08 10:33
abase0001:這題只是單純考你ITTO而已,別想得太複雜 05/08 10:35
daimond:同意B是合理答案,難怪覺得C像是又不像答案 XD 05/08 12:53
yule1224:這麼說來 FROM ABASE001 B 比較合理 05/08 13:20
yule1224:想想 挺對的 05/08 13:20
yule1224:你都已經知道了 目標(object) 但遲遲無法確定範圍的原因 05/08 13:21
yule1224:有可能是不知道公司有多少資源 可用 05/08 13:22
yule1224:BTW 有誰可以告訴我 組織過程資產在現實中是指什麼 05/08 13:23
chadtracy:LL 05/10 19:50
daimond:LL是其中一部份 組織過程資產是指所有相關的資訊或文字 05/10 23:46
daimond:或任何紀錄 例如專案成員的合照或技術執照培訓等 05/10 23:47
purist:B+1 05/11 00:57
LadySara:謝謝大家幫忙詳解,這題答案是B 05/11 10:21